Milestone Logistics Group

Milestone Logistics Group5 DownloadsNEWS ANCHOR:  We have breaking news! A 21st century logistics group that offers an efficient 3PL system, called Milestone Group Logistics, is making waves… Cut to: side screen playing Milestone ad NEWS ANCHOR:  Wow! Sounds like MGL […]

Murzan DUS-PIG Fixes

Murzan DUS-PIG Fixes102 DownloadsPlease note; the rest of this video assumes that the DUS discharge line has already been cleared out by using a Pig system, and that the machine has already been raised on its casters and relocated to […]

Murzan PC Pump-Reassembly

Murzan PC Pump-Reassembly25 DownloadsReassembly The PC pump can now be reassembled after being rebuilt and cleaned. Start by reattaching the diaphragm assembly to the pump. To do this, thread on one diaphragm assembly to the shaft. [VIDEO OF DIAPHRAGM SCREWING […]

Murzan PC Pump-Rebuild

Murzan PC Pump-Rebuild27 DownloadsPump Rebuild Once the pump has been disassembled, you are ready to begin rebuilding the centerblock. Please note; this video only covers the replacement of the components found in the P-1 CR kit. Please contact Murzan if […]

Murzan PC Pump-Disassembly

Murzan PC Pump-Disassembly28 DownloadsDisassembly Start by disassembling the pump to begin sanitation or maintenance activity. First, remove the suction manifold by detaching the two tri-clamp connections at the bottom of the product chambers. Please note; the check valves are attached […]

Murzan PC Pump-Intro-Preface

Murzan PC Pump-Intro-Preface30 DownloadsIntroduction The purpose of this video is to instruct our customers on the proper method of disassembly, rebuild, and reassembly for the Murzan PC pump for sanitation and maintenance activities. The PC pump is a very simple […]

Murzan DUS-Ready through Adjustments

Murzan DUS-Ready through Adjustments32 DownloadsYour DUS is now ready to be relocated and placed back into operation. Control Panel Adjustments The Murzan DUS control panel can be adjusted to better control the machine in each specific application. This section of […]

Murzan DUS-Reassembly through Dry Test

Murzan DUS-Reassembly through Dry Test33 DownloadsReassembly Prior to reassembly, ensure that the machine carriage is fully lowered and is not raised on the mobile casters. Begin by reattaching the diaphragm assemblies to the pump. Start by sliding the side that […]

Murzan DUS-Intro through Disassembly

Murzan DUS-Intro through Disassembly27 DownloadsThe purpose of this video is to instruct our customers on the proper method of disassembly and reassembly for the Murzan DUS during sanitation or maintenance activities. The system is designed for easy disassembly and reassembly, […]